WHICH GENERATOR IS RIGTH FOR YOU?

How do you size a generator?
NFPA 70 also known as the National electrical code, Art 702, addresses this requirement and states that standby non required power generators shall be capable to supply required power to all load connected to the generator, to meet this requirement the owner shall select the load that are to be connected to the emergency generator and do not exceed the capacity of the generator.

How much fuel does a Residential Emergency Home Standby generator use?

 

7 KW
Air-Cooled

12 KW
Air-Cooled

15 KW
Air-Cooled

15 KW
Liquid-Cooled

20 KW
Liquid-Cooled

25 KW
Liquid-Cooled

40 KW
Liquid-Cooled

Nat. Gas cu ft/hr

105

185

240

277

369

441

735

Lp Gas cu ft/hr (gal/hr)

44.1 (1.2)

79.0(2.17)

102.3 (2.8)

110 (3.1)

143 (4.0)

175 (4.8)

310 (8.8)

 

Figures are fuel consumption values at 100% (full) load. It is unlikely that the generator would run at full load for an extended period of time. Therefore, your consumption would decrease accordingly.

The generator that I've chosen has a 100-amp automatic transfer switch. What if I have 200-amp service in my home?
It is always recommended that emergency circuits be isolated by the emergency load center. An isolated sub-panel will prevent the possibility of the generator becoming overloaded. Thus, the system will respond automatically.

Will 200-amp automatic transfer switches be available for the air-cooled models, and the 15 kW and 20 kW liquid-cooled Residential Emergency Home Standby generators?
No. It is not electrically necessary. The outputs of these generators are safely carried with the 100-amp automatic transfer switch.

What is the expected life of the engine?
A properly maintained engine should provide over 20 years of operation under emergency standby conditions. Keep in mind that the units are not intended to provide continuous power (24 hours a day, 365 days a year).

Where can I purchase parts?
Parts may be obtained by contacting Empire Electric part department at 305-264-9982. Part numbers are located in the owner's manual.

What is the cost of a service/maintenance contract?
For service calls labor rates are $ 83.00 per hour, three hours minimum, plus travel time, plus the required materials or a yearly service contract, which includes two visit per year, two oil change, oil and air filter change check all part listed in the maintenance contract for 500.00 per year, paid at the commencing of the annual contract, plus damaged parts, if any.

How much oil does the engine crankcase hold?
Air-cooled: 7 kW, 12 kW and 15 kW – 1.7 qt.Liquid-cooled: 15 kW, 20 kW and 25 kW – 4.0 qt.

Liquid-cooled: 45 kW – 4.5 qt.

What type of oil is recommended?
The recommended oil for the 7 kW, 12 kW and 15 kW air-cooled units is 10W-30 temperatures above 20° F. Use 5W-20 or 5W-30 for temperatures below 20° F. After the first oil change, all-season 5W-30 synthetic oil may be used. API Service Class SG, SH or SJ should be used in all cases.

The recommended oil for the liquid-cooled units is 15W-40. All oil should be SAE rated high detergent oil that meets API Service Class SF requirements for gasoline engines.

Propane tanks are usually rated by pounds. Is there a conversion that can be applied to the fuel consumption numbers?
Yes. For general conversion, propane weighs 4.24 pounds per gallon. 1 lb. = 8.58 cu. ft.. 1 gallon = 36.39 cu. ft.

INSTALLATION OF THE GENERATOR

 

TO START THE PROCESS WE NEED FROM YOU:

 

·         HAVE A LICENSED GAS COMPANY CONTRACTED TO INSTALL THE GAS SUPPLY FOR THE GENERATOR, IF YOU DON’T HAVE A GAS COMPANY WE CAN REFER YOU SOMEONE.

·         PROVIDE US WITH A RECENT SURVEY OF THE PROPERTY FOR PERMITTING PURPOSES.

·         SIGN AND NOTARIZED THE CITY/COUNTY APPLICATIONS FOR PERMITS.

·         SIGN AND NOTARIZED NOTICE OF COMMENCEMENT FORM AS PER FLORIDA STATUES.

 

 

HOW LONG THE INSTALLATION TAKES

 

The air-cooled 7 kW, 12 kW and 15 kW, which comes equipped with a comprehensive installation kit, can take as little as 16 hours to have the actual installation performed, other permitting related procedures like to plan creation, plan processing, permit and inspections, may make the overall installation to take about two months, The liquid-cooled 15 kW to 45 kW generators will normally take from 2 days to 3 days. Air-cooled units are typically installed on a composite mounting pad. Liquid-cooled units, because of their additional weight, must be installed on a stronger mounting surface. The increased installation time is necessary to pour a concrete slab and allow for it to set properly. If the installer can source a prefabricated mounting pad that will meet the increased weight requirements of a liquid-cooled unit, the installation time will be reduced accordingly, but still a permitted work, will need to go to thru the permit procedures, that will make the overall installation to take about two months.

 

The length of time is based on a typical application. It does not apply to applications that require extended runs of conduit or gas piping or the placement of a unit far from the incoming gas or electrical service.

 

Typical timeframes:

 

a)       An average time frame for plan design, plan review by the local municipality and obtain the required permits, may take 4 weeks.

b)       Only after permits are obtained, the merchandise will be released in order to avoid restocking charge, back freight cost, and  the like in case the local jurisdiction or community refuse to accept the installation of the generator due to zoning set back or noise requirement etc.

c)       Once the generator arrives, the customer will be contacted to start the installation. Electrical installation of the generator will be completed within 5 working days; owner shall coordinate with the gas company to complete the work as soon as possible.

d)       An average installation takes from 8 weeks to 12 weeks from placing the order to final inspection; it all depends on job conditions, and requirements of the municipalities where the job take place.

 

 

WHAT IS THE COST OF THE INSTALLATION

 

                For Home Depot customers:

·         You paid the total contracted amount directly to Home Depot before the beginning of the process.

·         Once order is accepted, and released, a non refundable charge of $1500.00 for engineering and permitting cost will be charge in case or customer cancellation after the third day of installer receiving the order.

 

 

                For all other customers:

·         Once you approved our proposal, the schedule of payments is as follow:

·         $2,000.00 Deposit to start the installation process.

·         Price of the generator in order to place the order.

·         Balance of the proposal at the Final inspection approval.

 

 

Items that will lead to additional cost, and are not included in base cost:

 

a)    Meet flood elevation criteria for the location of the generator. Certain properties are located within flood zones, these areas may be required to raise the generator above flood elevation criteria, as set by local municipalities.

 

b)   Structural engineer calculations for pouring in place concrete slab, precast pads, or slabs made by the customer (if required by local jurisdiction)

 

c)   For liquid cooled, crane cost for job conditions where is required to fly the generator over the house, to the proposed location.

 

d)  Where required by the municipality, the installation of gas leak detector inside of the house will be at additional cost.

 

e)  Where requested by the municipality, if the master permit is required to be obtained by other than the electrical contractor (i.e. a general contractor or a mechanical contractor, etc) cost to hire this third party contractor will be at additional cost to the owner.

 

f)   Any other work mentioned in the scope of work, other work requested to be performed by others (i.e. inspectors, owner etc.)